According to the Forester Construction web site work is due to begin on the addition to the Morrison Clark Inn at 11th and L Street NW. In fact it has begun already.
|
Signage on 1107 L Street - clean-up in progress |
Removal of asbestos and hazardous materials from 1107 and the Chinese Church began about a month ago, according to one of the construction team. The facades of these two buildings will be maintained and restored, remodeling will only take place in the interior.
|
Church will be restored and facade retained (circa 1957) |
Some concern had been raised locally about the status of the 1700's carriage housed, that is located in the alley off of 11th Street, but the construction team member assured me that the building would be preserved.
UPDATE: There has been a structural problem with carriage house wall, following disruption of the roof. The wall is now slightly overhanging the alleyway (which has been closed for safety reasons)
Read on here,
an article from 'Preserving DC Stables' in their latest blog posting lays out the problem and some resolution.
UPDATE: The upper wall of the carriage house (to just below the windows) has been removed - it was tenuous at best - good job by Forrester maintaining the integrity of the structure as a whole. Read on here, Preserving DC Stables follow on article explaining
what happened and Forrester's response. Article includes photo's.
|
1700's Carriage House exterior will be preserved (one the oldest standing structures in DC) |
UPDATE: Construction work has begun on the exterior. L Street between 10th and 11th is now single lane traffic.
|
L Street between 10th and 11th are now single lane |
|
Exterior work begins on the Chinese Church structure |
The DC Permit, issued on April 4th, allows Forrester to occupy the curb lane adjacent to 1011 L Street, and is valid through September 27th, so if you travel this way you can expect delays.
|
L Street view of existing Inn and future addition |
Here is the text of the announcement from Forrester Constructions web site;
February 26, 2013 - Forrester Construction Company is pleased to
announce that it has recently begun work on the addition to the
Morrison-Clark Inn, located at 1015 L Street, NW, Washington, DC.
Originally built in 1864 and listed on the National Register of Historic
Places, the Victorian era hotel will be expanded by 43,000 square feet,
incorporating neighboring historic structures into the overall design.
The
new addition to the inn requires preservation of a 1700s carriage
house, one of the oldest buildings in Washington, DC, keeping the
exterior intact while completely renovating the interior. The facades of
a neighboring rectory and 1880s townhouse will also become part of the
space and will be maintained during construction by external bracing and
underpinnings. The hotel addition will be six stories with 56 guest
rooms featuring high-end finishes, a central courtyard connecting the
buildings and an expansion of the below grade parking garage.
For
more than a year, Forrester provided preconstruction services assisting
the owner and design teams in the development of multiple design
packages and a variety of cost saving strategies. The Forrester team
worked with Architecture, Inc., the architecture firm providing support
for the core and shell of the building. Forrester also partnered with
Forrest Perkins, the architecture firm outfitting the interiors.
“Combining
multiple historic facades into one hotel is quite exciting,” says Vic
Bonardi, Forrester vice president of preconstruction and design-build
services. “Our preconstruction work will be highly beneficial during the
construction process to ensure the project is delivered within the time-frame and budget outlined. This is a wonderful opportunity for
Forrester to leverage its extensive experience in the preservation of DC
historic buildings.” The project is scheduled to be complete by April
2014.
|
Morrison Clark Inn gardens beloved by local residents |
Update: Support exo-skeleton added to structures
|
Support Exo-Skeleton added to Chinese Church exterior |
|
Providing support while demolition continues |
Source:
Forrester Construction
Preserving DC Stables
FYI. There will be a meeting tomorrow (Tuesday, April 30th @ 5:30pm) about the new hotel expansion of the Morrison Clark (located on 1015 L St., NW). This is a very dense residential space, so some might be concerned about upcoming weekend work or traffic plans. This is a great opportunity to learn about the project and ask questions, which should be completed Summer 2014.
ReplyDeleteMorrison Meeting
Tuesday 30 April 5:30 - Morrison Clark Hotel, 1015 L Street (enter on 11th St)
Presentation on the construction/renovation/expansion of the Morrison Clark.
This project is approved and has completed a
It's good that construction in being resumed again. Some times the nearby buildings get affected in construction. Worker and engineers has to be more careful while construction when near by is some important building. Thanks for sharing the news.
ReplyDeleteAbout us: Top Construction Companies in uae