SHAW: South Shaw Community Update - 9th & L Street's Construction Schedule for Columbia Place
Rendering 9th Street NW looking South |
Milestone Activities Affecting the Community
- Project Start Date April 4th, 2016
- Alley Closure – April 4th, 2016
- Installation of Jersey Barriers - Alley to be Closed for Duration of Project
- Utility Work in the Alley – May/June 2016 (Subject to Change)
- The Whitman Parking Garage Traffic Adjusted
- Excavation Activities – May/June 2016
- Installation of Tower Crane #1 – August 2016
- Installation of Tower Crane #2 – September 2016
- Build Back of Sidewalks – Summer 2018
- Columbia Place Apartments Completion Date – September 2018
- Columbia Place Hotel Completion Date – November 2018